Ernst & Young was paid £33m for handling the administration of Metronet, the company which left the maintenance of two thirds of the London Underground in limbo when it collapsed.

The failure cost the taxpayer up to £410m, the National Audit Office also disclosed in a highly-critical report released today.

'The taxpayer has borne some of the direct costs of Metronet’s failure, including the unexpected upfront payment of £1.7bn. We estimate there has been a direct loss to the taxpayer of between £170m and £410m,' the NAO said.

The government had to shell out the £1.7bn to cover Metronet's debt obligations to its lenders, which would have been paid back over the course of the 30-year contract if the company had not collapsed.

'The main cause of Metronet’s failure was its poor corporate governance and leadership. Many decisions had to be agreed unanimously by five shareholders, which all acted as Metronet’s suppliers and had different motivations depending on their roles. The executive management changed frequently and was unable to manage the work of its shareholder-dominated supply chain effectively,' the NAO said.

The suppliers had power over some of the scope of work, expected to be paid for extra work undertaken and had better access to cost information than the management, the NAO said.

'The poor quality of information available to management, particularly on the unit costs of the station and track programmes, meant that Metronet was unable to monitor costs and could not obtain adequate evidence to support claims to have performed work economically and efficiently.'

The public sector watchdog called for an annual review of any future work, including an audit of financial models produced to improve the transparency of information about delays or cost overruns and make the Department for Transport aware of any risk to the taxpayer in any future.

The NAO added future Public-Private Partnership contracts should be awarded to bodies which had clear leadership, a credible corporate governance structure and an approach to securing suppliers which could clearly demonstrate value for money.

Visitor comments Add your comment

display:none

Add your comment

We won't publish your address


By submitting a comment you agree to abide by our Terms & Conditions

Your comment will be moderated before publication

Submit

Newsletters

Get the latest financial news sent directly to your inbox

  • Best Practice
  • Business
  • Daily Newsletter
  • Essentials

Careers

Search for jobs
Click to search our database of all the latest accountancy roles

Create a profile
Click to set up your profile and let the best recruiters find you

Jobs by email
Sign up to receive regular updates with the latest roles suitable for you

Briefings

Supplier Statement Reconciliations cover

Supplier statement reconciliations: Manual chore or critical value adding process?

By looking at the reasons supplier statements became unfashionable, and the reasons why it is different today, this paper delves into the many benefits that can be obtained by automating the process.

7 Building Blocks cover

7 building blocks for business growth

Having a real and true view of your organisation’s current financial position, and having the right systems and processes in place, will ensure that you can make strong choices and are ready to capitalise on opportunities